Building “A” slab-on-grade and high wall demolition is ongoing.  The lane adjacent to the high wall will be closed for the duration of demolition.

Building “E” appendage demolition is ongoing.  The lane adjacent to the appendage will be closed as needed.  A police detail will be present to help direct vehicular and pedestrian traffic.

The installation of the new underground electrical duct bank in front of the mall entrance will commence.  A police detail will be present to help direct vehicular and pedestrian traffic.