November 13, 2018

Excavation, concrete and plumbing work continues at Building “B2”, the future location of the parking garage near Marshalls.

Masonry restoration continues at Building “E”, the future home of City Works and Majestic Cinema, as well as interior metal framing and drywall, and roof work.

Removal of brick window openings for the second floor of Building “A”, the current home of Marshall’s and other retailers, has begun.

On Thursday evening, November 15th, starting at 10PM until 6AM, water will be shut off as a new water main line is connected.

Please reference the construction map for additional parking locations and accessibility.